Insurance deconstruction

Downer NZ

CASE STUDY
Cost minimization deconstruction advice and physical delivery
2021 - 2022
  • Flood waters compromised a recent bridge abutment concrete pour.
  • Site teams were unable to cost effectively undertake deconstruction.
  • We put innovation into practice by developing and implementing an expanding grout solution to manage deconstruction of in situ concrete.
  • Reinforcing steel was able to be retained in place.